Add a query for project - Jenkins (Admin):

Table of Content:

About

This document shows you how to add a query for every monday 08:00 each month in the sunshine project and remove the query test_02 from test.

How to:

  1. Go to Jenkins and your area in your current company. Find the right folder. Let us call it sunhsine. Click it.!200aa.png
  2. In this case, click the test_02 button.
    !201aa.png
  3. To the left, you will find a button called ‘Configure’. Click it.
    !202aa.png
  4. You are going to change the time in this query. Scroll down until you find a headline called Build Triggers. Click the button called Build periodically and type in the new schedule for the cronjob. In this case it is H 8 * * 1. In this case we want the task to run _At 08:01 on Monday'.
!! IMPORTANT !!

The first number 1 should be replaced by the letter H as seen in the picture below:

!203aa.png

Cronjob Schedule Explanations:
  1. The new configuration should now look like this picture below. Click the ‘Save’ button at the bottom of the page when this is done.!204aa.png
  2. Go back to the sunshine folder and click on the test.
    !205aa.png
  3. Find the button ‘Configure’ again and click that.
    !206aa.png
  4. Scroll down until you find a headline called ‘Post-build Actions'. Simply remove the ‘weeklynumbers’ by deleting the text.
    !207aa.png
    The new picture should look like this now.
    !208aa.png

And you are done. 😄